Backlash Adjustment (G86)
Special Tools J-25025-7A Dial Indicator Mounting Post J-8001 Dial Indicator Set Equivalent regional tools: Special Tools Procedure
- Install the J-25025-7A Dial Indicator Mounting Post and the J-8001 Dial Indicator Set to the axle housing.
- Set the J-8001 Dial Indicator Set so that the stem is aligned with the gear rotation and square to the tooth angle.
- Hold the drive pinion stationary, move the ring gear back and forth.
- Repeat the measuring procedure at eight points around the ring gear.
- The difference between the backlash at all of the measuring points should not vary by more than 0.05 mm (0.002 in).
- If the difference between the backlash at all of the measuring points varies by more than 0.05 mm (0.002 in), inspect for burrs, a distorted case flange or uneven bolting.
- If the difference between all the measuring points is within specifications, the backlash at the minimum lash point measured should be within the specification. Axle Preload and Backlash Specifications
- If the backlash is too small, increase the backlash using the following procedure:
- If the backlash is too large, decrease the backlash using the following procedure:
- Install the differential, spacer, and shims.
- Recheck the backlash and adjust if necessary.
- Return to the previous procedure and continue from appropriate step which linked to this procedure.